Client: Klemetsrudanlegget AS
Project: Carbon Capture Project “Klemetsrudanlegget AS”
Scope: Study
Date: April 2017 – September 2017
Mhrs: 6000 Mhrs
Location: Oslo – Norway
Selected sites for CCS project are:
Status:
Selection criteria:
The Scope of Work for this CCS project, was to prepare the design of a plant capable of capturing the CO2 from the KEA Energy-from-Waste and to make it available for pipeline transportation in a dense gas phase, liquefy it at the harbor and store it in interim storage tanks at harbor. The scope of work included the following main topics;
The final report consisted of: