Statfjord Øst Gas Lift​
Production on Statfjord East started in 1994 , including Water Injection. Production pressure has been decreasing since WI stopped in 2008. ​4-5 new wells is to be drilled, and gas lift is needed to aid the production.​ Production start-up is planned for 2024. ​​

Client

Equinor

Project

Statfjord East Gas Lift​

Scope

Execution Phase​

Date

2021-2023​

The Topside scope will be executed by Moreld Apply, and will have close interfaces with TechnipFMC, NOV and Halliburton for the Subsea scope. ​

Scope of Work​

  • Optimizing the process parameters to handle the new production rates and perform a full rebundle of 1st, 2nd and 3rd compressors.​
  • New 8‘’ fully welded gas lift flowline to be installed from C01 to C10, included four ESV’s (one with HIPPS), FE, FV and blow down valves .​
  • Methanol injection​
  • L and M flowline modification with cross over and material change.​
  • Replacement of bundle in 1st stage After Coolers.​
  • Replacement of Production Gas Metering Heater.​
  • Change Internals in Satellite Separator​
  • Install a temporary winch arrangement to pull out existing WI riser and pull in the new gas lift riser.​